Consisting of nine buildings and more than 1M sq. ft., Meta’s Menlo Park campus was constructed over a two-year period with the majority of work occurring in a very tight time frame from August to December.
The project included approximately 450,000 sq. ft. of office space, two new exterior skybridges/stairs, five acres of courtyard, two ground-up cooking facilities, skin renovations, a full service café and a dining facility featuring 6,500 pieces of pipe rail. Work was coordinated to allow Meta to move their entire workforce to the Menlo Park campus prior to the holiday season.

DETAILS
Meta
Menlo Park, CA
Corporate Office
1,000,000 SF +
LEED Gold
Various


The SC team had 14–16 weeks to do a large amount of work that included meeting LEED Gold standards. You company went the extra mile…they were doing things you would never ask a contractor to do.”
–John Tenanes
Meta


Photographer: Jasper Sanidad